To qualify for a grant, the RVO expects a flexibility scan and feasibility study to include, among other things, the following points:

  • analysis of electricity consumption profiles
  • Peak and off-peak analysis of electricity demand
  • 5-year forecast of energy consumption and growth
  • Estimated flexibility per measure (MW / MWh)
  • Analysis of deployment opportunities and control strategy
  • consult with the grid operator regarding grid impact and potential contracts

In addition to the points mentioned above, the following additional considerations apply to the feasibility study:

  • analysis of the scope of the measure(s)
  • contribution to congestion reduction through (flexible) contracts and the resulting financial revenue
  • investment costs, operating costs, and the pros and cons of the measure
  • the development of a conceptual technical design
  • an implementation plan that includes a phased approach and the organizational impact

Tip: Repowered has extensive experience in analyzing these components and providing clear insights, and ensures that your application is well-founded.